Project Update: ICM
Our team is hard at work at ICM in Colwich, with around 250 people on site working to have the plant operational by mid-summer. Production has recently begun on the lower level of the Wood Chip Building, a large facility with 30 inch thick walls on two sides and a wall height of 30 feet in several areas. We will also be starting the scrubber, acid containment and gasifier foundations in the next month. We will continue to keep you updated as we work toward completion!