Project Update – Fidelity Bank RISE: A Beacon of Progress
Conco crews are hard at work in downtown Wichita at the Fidelity Bank Car Park! Horizontal forming is well under way with the installation of temporary shoring. This will allow our crews to place reinforcement and place nearly 1,700 cubic yards of concrete on each elevated deck! After each deck is poured and cured, the shoring will be removed and re-used on each level.