Project Update – Fidelity Bank RISE: A Beacon of Progress

Despite the recent wet and inclement weather our crews at the Fidelity Car Park are making great progress! The 4th floor structure is well under way with half of the deck already poured. In early May we will start forming and pouring the columns for the 5th floor. We will also be able to open up the first floor area for other trades to begin work. Check out these pictures of the progress we’ve made so far!